Meter Poles

Sumter EMC provides guidelines for the installation of meter poles when underground or overhead service is required away from a building. 

Members are responsible for furnishing and installing the pole to specifications, including height, grounding, and equipment mounting, to ensure safe and reliable electric service connection.

Wired meter poles and meter pedestals are available for purchase from Sumter EMC for installations requiring a meter pole or meter pedestal. Sales and delivery are limited to locations inside Sumter EMC's service territory in Georgia.

Meter Poles

These wired meter poles are complete with meter socket, mast, and 200-amp main breaker (or, for irrigation pivots, 30 or 60 amp fused disconnects). The breaker box includes unused breaker positions suitable for connecting outdoor electrical equipment such as heat pumps and water pumps. Sumter EMC will also deliver and set the meter pole for an additional fee. See the fee chart below.

Installation

Installation - For delivery and installation of pole (with or without disconnect), and for pedestal, add $300.

A licensed electrician should install the wiring between the meter pole and the building. All permits required to receive service are the responsibility of the member.

25 Foot Meter Poles and Fused Disconnect Poles      *Effective May 1, 2026

PriceDescriptionTypical Application
$8825 Foot Pole (No Disconnect or Meter Base)Overhead service (bare pole only)
$1,00025 Ft. Pole with Meter Base and 240V/200 Amp DisconnectOverhead service to mobile home
$1,08025 Ft. Pole with 480V/30 Amp DisconnectOverhead service to irrigation pivot
$1,20025 Ft. Pole with 480V/60 Amp DisconnectOverhead service to irrigation pivot 

 

 

Meter Pedestals for Underground Service Connections      *Effective May 1, 2026

PriceDescriptionTypical Application
$1,300Pedestal with Meter Base and 240V/200 Amp DisconnectUnderground service to mobile home
$1,440Pedestal with 480V/30 Amp DisconnectUnderground service to irrigation pivot
$1,560Pedestal with 480V/60 Amp DisconnectUnderground service to irrigation pivot 

Important Notes

  1. Member's electrician is responsible for all local permits and wiring between disconnect and Member's equipment.
  2. These prices are fully assembled FOB Sumter EMC warehouse, Americus.
  3. All poles are new - CCA, Class 6.
  4. Installation and delivery are only available when the Sumter EMC crew is on-site to install Sumter EMC's service drop conductors.
  5. Member is responsible for wiring and installation on the load side of breakers or disconnect and for all maintenance after installation.
  6. Sumter EMC and Members should always spot the service pole location before installation.
  7. The local governmental jurisdiction requires electrical inspections after the wiring is completed and before the meter is set. Member is responsible for obtaining any permits needed from the local jurisdiction. 

Contact our Member Services Department by clicking below or call 1-800-342-6978 for additional details.